Online

UK estimate examples

Four examples for Kitchen, Bathroom, WC and Cloakroom.

Company templates
DEMO · GBP

Demonstration data, editable for presentations. Changes stay on this page and are lost on reload; export a CSV to keep them.

Materials
£2,344.30
Labour
£2,910.00
Demo price excluding VAT
£7,724.90

Standard bathroom

6 m² floor · 18 m² tiled walls

Example assumptions

Like-for-like replacement; normal access; reasonably sound substrate. Includes strip-out, local services, waterproofing, tiling, sanitaryware and finishing. Days are cumulative effort, not project duration.

Exclusions

Excludes structural work, asbestos, moving soil stacks, boiler, underfloor heating and major substrate repairs.

Materials

£2,344.30

Budgeted quantities include waste and rounding to the stated pack size. Adjust dependent materials, such as adhesive, separately.

White ceramic wall tile

m² · Purchase increment: 0.9Public reference
Budgeted quantity: 19.8 m²£267.30

Porcelain floor tile

m² · Purchase increment: 1Demo assumption
Budgeted quantity: 7 m²£140.00

Flexible tile adhesive

20 kg bag · Purchase increment: 1Public reference
Budgeted quantity: 6 20 kg bag£96.00

Tile grout

5 kg bag · Purchase increment: 1Demo assumption
Budgeted quantity: 2 5 kg bag£36.00

Backing, primer and waterproofing

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£280.00

WC, basin, vanity, bath, taps and screen

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£1,150.00

Pipework, traps and fittings

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£150.00

Extractor, light and electrical accessories

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£140.00

Bathroom paint, silicone and consumables

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£85.00

Labour

£2,910.00

One person-day = 8 hours of effort in this example. Daily work is budgeted in 0.25-day steps; fixed-price lines cover separate jobs.

Strip-out and preparation · labourer

person-day · Purchase increment: 0.25Public reference
Budgeted quantity: 2 person-day£360.00

Plumber · installation and checks

person-day · Purchase increment: 0.25Public reference
Budgeted quantity: 3 person-day£975.00

Tiler · waterproofing, tiling and grouting

person-day · Purchase increment: 0.25Public reference
Budgeted quantity: 4 person-day£1,000.00

Electrician · connections and checks

person-day · Purchase increment: 0.25Public reference
Budgeted quantity: 1 person-day£325.00

Decorator · preparation and finishing

person-day · Purchase increment: 0.25Public reference
Budgeted quantity: 1 person-day£250.00

Other costs

£400.00

Waste removal

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£280.00

Delivery and protection

allowance · Purchase increment: 1Demo assumption
Budgeted quantity: 1 allowance£120.00
Sources and assumptions References checked on 2026-09-19

Demo prices are chosen allowances, not current supplier quotations. Check availability, price and VAT treatment before using them for a job.

Lines without a source are planning assumptions. There is no automatic allowance for London, difficult access or building condition.

B&Q · 3 m laminate worktops

Reference for selected 3 m worktops: £204. Chosen demo allowance: £170/item excluding VAT. Finish and availability need checking.

GOV.UK · VAT rates

20% is the demonstration scenario. Actual treatment depends on the work and tax circumstances; this calculator does not determine it.